PROJECT COST CONTROL IN THE NIGERIAN CONSTRUCTION INDUSTRY (A CASE STUDY OF EL-ALAN CONSTRUCTION COMPANY LIMITED)

Format: MS WORD  |  Chapter: 1-5  |  Pages: 75  |  4251 Users found this project useful  |  Price NGN5,000

  DOWNLOAD THE COMPLETE PROJECT

PROJECT COST CONTROL IN THE NIGERIAN CONSTRUCTION INDUSTRY (A CASE STUDY OF EL-ALAN CONSTRUCTION COMPANY LIMITED)

CHAPTER ONE

INTRODUCTION

1.1 Background of the Study

 In construction almost all clients are interested in obtaining gully functional facilities completed in time, cost, quality and scope. A builder who is able to construct within the estimated time and budget, to the right standards and scope is an excellent builder. Cost control is a process where the construction cost of the project is managed through the best methods and techniques so that the contractor does not suffer losses when carrying out the activities of the project. One of the aims of cost control according to George et. al (2012), is to construct at the cheapest possible costs consistent with the project objectives. Ultimately the decision of the manager that something should be done differently and the translation of that decision into practice are the actions to achieve control (Harris and McCaffer, 2002). Raina (1999) observes that it is of little use after a process has been completed to discover that its cost was actually too much. Most project managers and contractors in Nigeria find difficulty in controlling costs on their construction sites due to a number of problems which include poor project preparation, lapse in management and control, over budgeting, poor materials, labour shortages, increased cost of materials, delays in deliveries, wastage of materials, unexpected weather changes, loss of materials, insecurity and poor communication. This results into cost and time overruns, conflicts, and sometimes abandoning projects. This study was therefore carried out to identify the cost control techniques used in Ibadan, Oyo State and recommended to stakeholders who do not follow proper monitoring programs and cost controlling techniques.

1.2 Statement of the Problem

According to Seeley (1979) Ashworth (1999) Ayodele (2005) cost control techniques include the followings: approximate estimate, cost plan, bill of quantities, interim valuation/ stage payment, valuation of variation, fluctuation, final account preparation and cost analysis.

The Bill of Quantities, according to NIQS (2008) shall fully describe and accurately represent the quantity and quality of work to be carried out. Each of the sheets on which the bill of quantities is made has four different columns.

a) Description column- Contains the descriptions of the type and quality of materials to be expended on the works.

b) Quantity column- contains the quantities of materials to be expended on the job will take i.e basis of the preparation of program of work.

c) Rate Column- contain the unit rate i.e naira/ unit of materials to be utilised on the work. This forms the basis on which the cost of work is calculated.

d)  Amount Column- Contain the total cost of work for each of the elements.

Summarily show below:

1. Description column- Quality

2.  Quantity Column- Time

3.  Rate Column- Cost

4.  Amount Column

The above four columns which represent Quantity, Time and Cost is not limited to Bill of Quantities only, other techniques of cost control e.g interim valuation/stage payment, valuation of variation, valuation of fluctuation etc. are adequately represented by/or taken care of, by the columns.

It has been observed that many building projects development in Nigeria do not bother about the use of cost control techniques. This is corroborated by Ogunsemi (2002) who discovered that the non-use of cost control has contributed to the incessant building collapse in Lagos state of Nigeria. To minimise the building collapses, this study is set to determine the effect of conformance to or utilization of Bills of Quantities by government and private developers on building projects in Nigeria on the parameters of quality, delivery time and cost.

1.3 Objectives of the Study

The main objective of this study is to determine the effect of compensation management on employee performance. Specific objectives include;

i. Compare the effects of the use of cost control techniques on quality of construction project of government and private developers.

ii. Compare the effects of the use of cost control techniques on cost of construction projects of government and private developers.

iii. Compare the effects of the use of cost control techniques on delivery period of construction projects of governments and private developers.

1.4 Research Questions

i. What is the impact of cost control on construction activities in Nigeria?

ii. What is the effect of cost control on successful construction in Nigeria?

iii. What is the impact of cost control on construction project delivery timeline?

1.5 Research Hypotheses

Hypothesis I

H0: There is no significant impact of cost control techniques on quality of construction project of government and private developers.

Hi: There is significant impact of cost control techniques on quality of construction project of government and private developers.

Hypothesis II

H0: There is no significant impact of cost control techniques on cost of construction projects of government and private developers.

Hi: There is significant impact of cost control techniques on cost of construction projects of government and private developers.

Hypothesis III

H0: There is no significant impact of cost control techniques on delivery period of construction projects of governments and private developers.

Hi: There is significant impact of cost control techniques on delivery period of construction projects of governments and private developers.

1.6 Significance of the Study

The Nigerian construction sector is facing some challenges in which a greater percentage of the problems are management oriented. It is therefore important to plan and ensure due process in the management of construction projects so to achieve the best practice and quality delivery of the products. Also, this research work will enable the entire construction actors (i.e. clients, contractors and consultants) to be able to appreciate the importance of best practice of construction management in Nigeria right from the design stage to the commissioning stage.

1.7 Scope of the Study

The scope of this research is limited to construction management activities in Nigeria. The research is targeted to know how construction management is practiced and the management tools used in practice. The result will be analyzed using basic statistical method.

1.8 Limitations of the study

The demanding schedule of respondents made it very difficult getting the respondents to participate in the survey. As a result, retrieving copies of questionnaires in timely fashion was very challenging. Also, the researcher is a student and therefore has limited time as well as resources in covering extensive literature available in conducting this research. Information provided by the researcher may not hold true for all research under this study but is restricted to the selected respondents used as a study in this research especially in the locality where this study is being conducted. Finally, the researcher is restricted only to the evidence provided by the participants in the research and therefore cannot determine the reliability and accuracy of the information provided. Other limitations include;

Financial constraint: Insufficient fund tends to impede the efficiency of the researcher in sourcing for the relevant materials, literature or information and in the process of data collection (internet, questionnaire and interview).

Time constraint: The researcher will simultaneously engage in this study with other academic work. This consequently will cut down on the time devoted for the research work.

  DOWNLOAD THE COMPLETE PROJECT

PROJECT COST CONTROL IN THE NIGERIAN CONSTRUCTION INDUSTRY (A CASE STUDY OF EL-ALAN CONSTRUCTION COMPANY LIMITED)

Not The Topic You Are Looking For?



For Quick Help Chat with Us Now!

+234 813 292 6373

+233 55 397 8005


HOW TO GET THE COMPLETE PROJECT ON PROJECT COST CONTROL IN THE NIGERIAN CONSTRUCTION INDUSTRY (A CASE STUDY OF EL-ALAN CONSTRUCTION COMPANY LIMITED) INSTANTLY

  • Click on the Download Button above.
  • Select any option to get the complete project immediately.
  • Chat with Our Instant Help Desk on +234 813 292 6373 for further assistance.
  • All projects on our website are well researched by professionals with high level of professionalism.

Here's what our amazing customers are saying

Ibrahim Muhammad Muhammad
Usmanu danfodiyo university, sokoto
It's a site that give researcher student's to gain access work,easier,affordable and understandable. I appreciate the iproject master teams for making my project work fast and available .I will surely,recommend this site to my friends.thanks a lot..!
Excellent
Stancy M
Abia State University, Uturu
I did not see my project topic on your website so I decided to call your customer care number, the attention I got was epic! I got help from the beginning to the end of my project in just 3 days, they even taught me how to defend my project and I got a 'B' at the end. Thank you so much iprojectmaster, infact, I owe my graduating well today to you guys...
Excellent
Abdulrazak Bello Marsha
Usman Dan fodio University
It was quite a better guide for project and paper presentation purpoting. Many thanks.
Average
JONNAH EHIS
Ajayi Crowther University, Oyo
I was scared at first when I saw your website but I decided to risk my last 3k and surprisingly I got my complete project in my email box instantly. This is so nice!!!
Excellent
Temitayo Ayodele
Obafemi Awolowo University
My friend told me about iprojectmaster website, I doubted her until I saw her download her full project instantly, I tried mine too and got it instantly, right now, am telling everyone in my school about iprojectmaster.com, no one has to suffer any more writing their project. Thank you for making life easy for me and my fellow students... Keep up the good work
Very Good
Uduak From Uniuyo
IProjectMaster is the best project site for students. Their works are unique and free of plagiarism!
Excellent
Abraham Ogbanje
NATIONAL OPEN UNIVERSITY OF NIGERIA
At first I was afraid.. But I discovered they are legit. I will bring more patronize
Very Good
MATTHEW NGBEDE
Ahmadu Bello University
I wish I knew you guys when I wrote my first degree project, it took so much time and effort then. Now, with just a click of a button, I got my complete project in less than 15 minutes. You guys are too amazing!
Excellent
Peace From Unilag
I cried not knowing how to go about my project but the day i searched online and saw iprojectmaster, i called and got my full project in less than 15minutes, i was shocked!
Excellent
Musa From Ahmadu Bello University
Thank you iprojectmaster for saving my life, please keep it up and may God continue to bless you people.
Excellent

FREQUENTLY ASKED QUESTIONS

How do I get this complete project on PROJECT COST CONTROL IN THE NIGERIAN CONSTRUCTION INDUSTRY (A CASE STUDY OF EL-ALAN CONSTRUCTION COMPANY LIMITED)?

Simply click on the Download button above and follow the procedure stated.

I have a fresh topic that is not on your website. How do I go about it?

How fast can I get this complete project on PROJECT COST CONTROL IN THE NIGERIAN CONSTRUCTION INDUSTRY (A CASE STUDY OF EL-ALAN CONSTRUCTION COMPANY LIMITED)?

Within 15 minutes if you want this exact project topic without adjustment

Is it a complete research project or just materials?

It is a Complete Research Project i.e Chapters 1-5, Abstract, Table of Contents, Full References, Questionnaires / Secondary Data

What if I want to change the case study for PROJECT COST CONTROL IN THE NIGERIAN CONSTRUCTION INDUSTRY (A CASE STUDY OF EL-ALAN CONSTRUCTION COMPANY LIMITED), What do i do?

Chat with Our Instant Help Desk Now: +234 813 292 6373 and you will be responded to immediately

How will I get my complete project?

Your Complete Project Material will be sent to your Email Address in Ms Word document format

Can I get my Complete Project through WhatsApp?

Yes! We can send your Complete Research Project to your WhatsApp Number

What if my Project Supervisor made some changes to a topic i picked from your website?

Call Our Instant Help Desk Now: +234 813 292 6373 and you will be responded to immediately

Do you assist students with Assignment and Project Proposal?

Yes! Call Our Instant Help Desk Now: +234 813 292 6373 and you will be responded to immediately

What if i do not have any project topic idea at all?

Smiles! We've Got You Covered. Chat with us on WhatsApp Now to Get Instant Help: +234 813 292 6373

How can i trust this site?

We are well aware of fraudulent activities that have been happening on the internet. It is regrettable, but hopefully declining. However, we wish to reinstate to our esteemed clients that we are genuine and duly registered with the Corporate Affairs Commission as "PRIMEDGE TECHNOLOGY". This site runs on Secure Sockets Layer (SSL), therefore all transactions on this site are HIGHLY secure and safe!